Employing solutions to improve travel-time reliability of the road network

Michigan DOT TSMO strategies and project prioritization help improve corridor safety, congestion, and reliability

Jason Firman / January 24, 2020
I-96 Diverging Diamond Interchange at Cascade Road
I-96 Diverging Diamond Interchange at Cascade Road. Image: Michigan DOT

Through strong leadership and key champions across the agency, the Michigan DOT (MDOT) has built a foundation and culture that supports not only strategies and solutions to improve safety and mobility, but also operations program funding and project prioritization.

MDOT employs Transportation Systems Management and Operations (TSMO) strategies and solutions to provide more efficient use of existing transportation resources by implementing strategies, deploying technologies, and integrating systems to address freeway and arterial congestion, improve safety and mobility, and encourage sustainability.

To help overcome operations program and project funding challenges, MDOT developed the Trunkline Program Operations Template and provided funding that specifically supports TSMO project strategies and solutions. This template is intended to provide funding for an integrated program to optimize the performance of existing multimodal infrastructure by implementing systems, services, and projects to maximize capacity and/or improve the security, safety, and reliability of the transportation system.

New federal rules require states to measure, monitor, and set goals based upon a composite index of travel-time reliability metrics. Travel-time reliability measures how consistent the travel time is from one point to another, from one day to the next. Federal regulations require states and Metropolitan Planning Organizations (MPOs) to use three performance measures for assessing travel-time reliability. Travel-time data used to calculate each measure is purchased by the Federal Highway Administration (FHWA) and made available for use by states and MPOs. The vehicle probe data set used for the federally required measures is called the National Performance Management Research Data Set (NPMRDS). The data is processed through an analytical software tool known as Regional Integrated Transportation Information System (RITIS). The travel-time reliability measures, as defined in the PM3 federal rule are:

  • Level of Travel-Time Reliability (LOTTR) on the interstate: % of person-miles traveled on interstate that are reliable.
  • LOTTR on the non-interstate NHS: % of person-miles traveled on the non-interstate NHS that are reliable.
  • Freight reliability measure on the interstate: Truck Travel-Time Reliability (TTTR) Index.
Table 1: PM3 Reliability Measures – Final State of Michigan Targets
Table 1: PM3 Reliability Measures – Final State of Michigan Targets

Communications, planning, and execution

MDOT established two new funding programs totaling $50 million annually that focus on improving travel reliability, congestion, operations, and safety of traffic on the freeway and non-freeway network. Project selection occurs through the annual Highway Call for Project (CFP) process. A subcommittee of the CFP was established to review and recommend projects and ensure the program/project is meeting goals, strategic direction, and funding targets. The subcommittee, composed of central office and region members, developed criteria for project evaluation. Regions submit candidate projects for consideration annually, as part of the CFP. These programs use a wide range of funding sources: Federal Surface Transportation Program, National Highway Performance Program, Highway Safety Improvement Program (HSIP), Congestion Mitigation and Air Quality (CMAQ), and state “M” funds.

TSMO planning, strategies, and deployment

The information below provides the data-driven analytics used to calculate MDOT Operations Freeway and Non-Freeway program project prioritization. Each element of this scoring system had to be easy to understand, meaningful, and not overly burdensome to produce. Roughly 20 different performance measures were considered, and the process narrowed it down to six to seven different measures. These measures also allow the ability to compare a diverse range of projects to ensure the best projects are selected. Some example type projects include:

  • Flex route (Active Traffic Management, hard shoulder running, ramp metering, etc.)
  • Weave/merge lanes
  • Roundabouts
  • Signals improvements (detection, adaptive corridor systems, etc.)
  • Turn lanes
  • Safety improvements
  • ITS devices
  • Interchange/intersection improvements

Operations Freeway Scoring (total 100 points):

  • (30 points) Benefit/cost ratio
  • (30 points) Overall benefit
  • (15 points) Safety benefit (time of return)
  • (10 points) Combining with an existing project
  • (7.5 points) Planning time index > 2 or LOTTR > 1.5
  • (7.5 points) Travel time index > 1.5

Operations Non-Freeway Scoring (total 100 points):

  • (30 points) Benefit/cost ratio
  • (25 points) Overall benefit
  • (20 points) Duration since last awarded project in region
  • (10 points) Safety benefit (time of return)
  • (5 points) Planning time index > 2 or LOTTR > 1.5
  • (5 points) Level of service: E or F, or travel time index > 1.5
  • (5 points) Combining with an existing project
U.S. 23 Flex Route active traffic management system
U.S. 23 Flex Route active traffic management system

Outcome, benefit, and takeaways

A key component of these programs was to improve the reliability of the road network and to address the federal reliability requirements. To ensure MDOT is accomplishing this goal, a before-and-after analysis will be performed on all projects. An example analysis was performed on U.S. 23 just north of Ann Arbor where an active traffic management system was recently constructed. This included hard shoulder running, managed lanes, variable advisory speeds, and a queue warning system.

Figures 1 and 2 show the travel time for Southbound U.S. 23 in the AM peak through the project limits. The existing condition was shown to be somewhat congested and quite unreliable. After construction the congestion was all but eliminated and is now considered a reliable segment.

Figure 1: Travel Time: SB U.S. 23 between M-14 and 9 Mile Road/M-36 before construction.
Figure 1: Travel Time: SB U.S. 23 between M-14 and 9 Mile Road/M-36 before construction.
Figure 2: Travel Time: SB U.S. 23 between M-14 and 9 Mile Road/M-36 after construction.
Figure 2: Travel Time: SB U.S. 23 between M-14 and 9 Mile Road/M-36 after construction.

Conclusion

MDOT has secured a dedicated source of TSMO funding to improve corridor safety, congestion, and reliability, separate from traditional reconstruction and rehabilitation funds. These funds work together with ITS, signals, and safety according to the MDOT Trunkline Program Operations Template and align with operational strategic areas of focus in the MDOT Organizational Strategic Plan and the MDOT TSMO Implementation and Strategic Plan. The Freeway and Non-Freeway programs are in the first year of performance and align well with meeting goals of MDOT’s TSMO strategic plan. After the first year of project submittals, very little changes have been requested of the program. The scoring systems have identified the best projects to move forward and as the programs mature, adjustment will be evaluated to ensure they meet the current internal and external customer needs of safety and reliability.

About the Author

Firman is Congestion & Reliability Manager at the Michigan DOT.

Related Articles

Just a few months ago, U.S. roadways began to see a decline in roadway traffic as a result of the coronavirus (COVID-19) pandemic canceling major…
July 31, 2020
State Street Chicago
State Street in Chicago is considered a high-crash corridor. All images: Chicago DOT
In 2016, the City of Chicago adopted the ambitious goal of Vision Zero—eliminating all traffic fatalities and serious injuries.  Since the initial…
July 29, 2020
The worldwide spread of the COVID-19 pandemic has had profound effects on how Austin residents and visitors use transportation and move throughout…
July 23, 2020
Screenshot taken from OptaSense Traffic Monitoring Solution indicating average traffic speed and journey times between distance points.
Screenshot taken from OptaSense Traffic Monitoring Solution indicating average traffic speed and journey times between distance points.
Managing the impact of rapidly increasing traffic volumes and minimizing congestion and journey times on existing road infrastructure is a…